Contractor's Induction Guide


Please read all files below that make up part of this Induction Guide prior to attending the School to complete the work that you have been contracted to carry out. 

This guide is designed to give contractors information on Brisbane Catholic Education's (BCE) Workplace Health and Safety (WHS) Contractor Management System and provide specific requirements when working at a BCE School. 

The key purpose of this guide is to advise of:

· work health & safety obligations - WHS Act 2011 & WHS Regulation 2011

· hazards and their associated controls relevant to schools and BCEO, and

· any relevant operational issues in the management of contractors.

 

 

INSTRUCTIONS: 

  1. Read Contractor Induction Manual 
  2. Determine whether a Minor Contract or Major Contract by reading Contractor Classification Checklist
  3. If Minor Contract, read Contractor Checklist - Site Specific Requirements.
  4. If Major Contract (but no Principal Contractor), read Contractor Checklist - Site Specific Requirements and Contractor Safety Plan
  5. Complete Contractor Induction Register
  6. Bring completed Contractor Induction Register to the School Office on the day you are completing the work 
 1. Contractor Induction Manual 

2. Minor Contract or Major Contract?

Are you considered a Minor Contract or a Major Contract? Please click link "Contractor Classification Checklist" below to determine whether a Minor Contract or a Major Contract

Contractor Classification Checklist 

3. MINOR CONTRACTS

Contractor Checklist - Site Specific Requirements

4. MAJOR CONTRACTS

Contractor Checklist - Site Specific Requirements 

Contractor Safety Plan

According to s299 WHS Regulation 2011, a Safe Work Method Statement (SWMS) is required for high risk construction work. S291 WHS Regulation 2011, shows what is defined as high risk construction work. S303 requires the contractor to keep a SWMS until the high risk construction work is completed.  

5. Contractor Induction Register 

 

6. Bring signed "Contractor Induction Register" with you to the School Office on the day you are completing the work you have been contracted to do.

 

Download the Complete Contractors' Induction Guide including all Forms as listed below:

​Form 1 Contractor Classification - This is only for Major Contractors - refer to the School Office

Form 2 Contractor Induction Manual

Form 3 Site Specific Requirements

Form 4 Contractor Induction Register

Form 5 Contractors Safety Plan​